We are close to the finish line when the appliance package is delivered.
Appliance packages are decided farther in advance than most people realize.
The power requirements and sizes of special appliances are needed by the mechanical subcontractors before drywall is installed.
The list of these items are also confirmed with the cabinet builder before he begins – sometimes six to eight weeks in advance.